NEW CHURCH CONSTRUCTION PROJECT DASHBOARD

Construction Project Progress
Milestones
Progress

 Construction project Progress DashboardAs of December 31, 2009

Current Phase:

Phase 1, Church and Lower Hall

Target Date:

December, 2010

1.  Land Acquisition & Purchase

Complete

2.  Rezoning of Land for Church use Complete
3.  Site Plan Approval Complete
4.  Underground Services & Land Leveling Complete
5.  Detail Drawings & Building Permit 90 %
6.  Mobilization & Excavation 67 %
7.  Phase 1 Foundation Work 23 % North Elevation
8.  Lower Level Walls & Shafts Not Started
9.  Main Level Walls & Towers Not Started
10. Main Level & Mechanical Not Started
11. Exterior Envelop & Roof System Not Started
12. Interior & Electrical Not Started
13. Interior Millwork & Painting Not Started
14. Parking & Landscaping Not Started
15. Occupancy Permit & Demobilization Not Started

 

Financial Status
Outstanding Obligations

 As of December 31, 2009

2009 Fundraising Target

1.  Land Loan

$ 560 k.

2.  Land Prep & Servicing $ 177 k.
3.  Permits & Licenses $ 273 k.
4.  Consultants $ 130 K.
5.  Construction Deposit $ 60 k.

Total

$ 1.2 Mill
   

Total Cost of Construction: $ 7.5 Million

Required Cash Down: $ 2.5 Million

Construction Loan Amount: $ 5.0 Million

plus any outstanding obligations

Cost of Construction 
1. By End of December, 2009 $ 400 k.
2. By End of March, 2010 $ 1.87 Mill
3. By End of June, 2010 $ 1.75 Mill
4. By End of September, 2010 $ 2.35 Mill
5. By End of December, 2010 $ 640 k.
6. Final Payment & Change orders $ 490 k.

Total

$ 7.5 Mill
Tags: Project, New Church, Construction, Building